The Kerala State Electricity Board has issued a formal revised administrative sanction of <b>Rs 632.59 crore</b> for the 60-MW Pallivasal Extension Scheme. Originally approved in 2001 for <b>Rs 175.86 crore</b>, the hydropower project faced massive over two decades of delays and contractual changes before its commissioning in March 2026. According to KSEB documents, the final completion cost includes miscellaneous works, interest, employee expenses, and administrative charges. The board has also decided to conduct an independent study through an external agency to review project management practices and prevent future delays.