Infrastructure projects costing Rs 150 crore and above have recorded a cumulative <b>cost overrun</b> of approximately Rs 3.28 lakh crore, pushing their combined revised cost to Rs 38.11 lakh crore. The Ministry of Statistics and Programme Implementation monitored 1,862 ongoing projects across 17 central ministries in its October report. Out of the total ongoing projects, 649 have achieved over 80 percent physical progress, while 326 projects crossed 80 percent financial completion. The Transport and Logistics sector accounts for the largest share with 1,324 ongoing projects.